How to Measure and Value the Works under the 1999 FIDIC Red Book

red carpet on stairs in building

“The methods of measurement and valuation should be specified clearly to avoid future disputes.”

In accordance with Clause 12 [Measurement and Evaluation], Works should be measured and valued for payment.

In the beginning of the process, the actual quantities have to be measured.

The Engineer gives Notice to the Contractor’s Representative and then the measurement procedure begins.

Afterwards, the appropriate rate or price should be determined.

While determining the appropriate rate or price;

The rate or price specified for the item in the contract may be the appropriate rate or price.

If there is no such item, the rate or price specified for similar work will be the appropriate rate or price.

In certain circumstances, a new rate or price may be appropriate.

Ultimately, the Engineer determines the value of each item of work by applying the measured quantities and rates or prices in accordance with Sub-Clause 12.3 [Evaluation].

In this document, you will find the key issues and the procedure for the measurement and valuation of the Works under the 1999 FIDIC Red Book.

Steps of Measurement

and Evaluation

Procedure

01


Notice to the Contractor’s Representative

02


Measurement Procedure

03


Agreement or Determination of the Measurement

04


Selecting the Appropriate Rate or Price

05


Evaluation of the Works

1   Notice to the Contractor’s Representative 

The Engineer is to give a Notice to the Contractor’s Representative for the measurement of the works.

2   Measurement Procedure

The details to be considered are [1];

(a) Measurement shall be made of the net actual quantity of each item of the Permanent Works, and,

(b) The method of measurement shall be in accordance with the Bill of Quantities or other applicable schedules.

Measurement Process

1.  While realizing the measurement, the Contractor’s Representative is to;

Attend or send a qualified representative to assist the Engineer.

Provide the particulars that are required  by the Engineer.

2.  If the Contractor fails to attend or send a representative,  the measurement made is to be accepted as accurate.

Measurement from Records

Permanent Works are to be measured from records except as otherwise stated in the Contract. And, these records are to be prepared by the Engineer.

1.  The Contractor is to attend to examine and agree the records with the Engineer, and shall sign the same when agreed.

2.  If the Contractor fails to attend, the records are to be accepted as accurate.

3   Agreement or Determination of the Measurement

If the Contractor examines the measurement records but does not agree with the Engineer regarding the  measurement.

1.  The Contractor is to give a Notice to the Engineer  in relation to the records’ being inaccurate.

If the Contractor fails to give a Notice to the Engineer within 14 days after being requested to examine the records, the records are to be accepted as accurate.

2.  After receiving  a Contractor’s Notice;

The Engineer is to review the records and either confirm or vary them.

4   Selecting the Appropriate Rate or Price

The appropriate rate or price for each item is  to be specified in the Contract or specified for similar work (if there is no such an item).

A new rate or price is to be appropriate for an item of work if [2]:

(a)/(i) The measured quantity of the item is changed by more than 10% from the quantity of this item in the Bill of Quantities or other Schedule.

(ii) This change in quantity multiplied by such specified rate for this item exceeds 0.01% of the Accepted Contract Amount.

(iii) This change in quantity directly changes the Cost per unit quantity of this item by more than 1%, and

(iv) This item is not specified in the Contract as a “fixed rate item”:

or

(b)/(i) The work is instructed under Clause 13 [Variations and Adjustments].

(ii) No rate or price is specified in the Contract for this item, and

(iii) No specified rate or price is appropriate because the item of work is not of similar character,  or is not executed under similar conditions, as any item in the Contract.

Each new rate or price is to be produced from any relevant rates or prices that are specified in the Contract with fair adjustments in accordance with the above mentioned paragraphs.

Otherwise, it is to be derived from the reasonable cost of executing the work and profit, assessing any other relevant matters.

5   Evaluation of the Works

By evaluating each item of the work, the Engineer is to proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine the Contract Price applying;

1.  The measurement agreed or determined in accordance with Sub-Clause 12.1 [Works to be Measured] and 12.2 [Methods of Measurement].

2.  The appropriate rate or price for the item.

FOOTNOTES

1. The same Sub-Paragraph letters are used as in Sub-Clause 12.2 [Method of Measurement] of the 1999 FIDIC Red Book.

2. The same Sub-Paragraph letters are used as in Sub-Clause 12.3 [Evaluation] of the 1999 FIDIC Red Book.

This information is provided for your convenience and does not constitute any “Legal Advice”. This document is prepared for the general information of the interested persons. This should not be acted upon in any specific situation without appropriate legal advice.

This information may not be reproduced or translated without the prior written permission of eayglobal.com

For further information please contact eay@eayglobal.com



Grow Your Knowledge

Your subscription could not be saved. Please try again.
A confirmation email is on the way. Follow the instructions and check the spam folder. Thank you.

Recent Publications

  • eay@example.com
  • San Francisco, USA

Discover more from EAY GLOBAL

Subscribe now to keep reading and get access to the full archive.

Continue reading